Lagos-Ibadan Railway: Work Starts On Lagos Roads (Photos) -Nigerian

Before you go! Share this content on any social media platform

Afterwards, the Lagos-Ibadan Railway is finally making its way into Lagos. As seen in the pictures available to AutoReportNG, workers were seen doing site clearance for Agbado Station and Ijoko Station in preparation for the railway track.

So, by the end of October, 51% of excavation, 80% of filling works, 100% of bridge foundation, 67% of abutment and 70% of bridge piers have been completed. For records so, the beam laying for Onigbongbo Bridge was completed on 3 November 2018.

These are some pictures from the site …



Beam laying for Onigbongbo Bridge was completed on 3 November 2018


Site clearance for Agbado Station and Ijoko Station are in progress

source:
https://www.autoreportng.com/2018/11/lagos-ibadan-railway-work-starts-on.html

Before you go! Share this content on any social media platform

Source link

SOURCES:NAIJALOADED.COM.NG TOOXCLUSIVE.COM
OSUNDEFENDER.COM 360NOBS.COM WAKANDA.NG

Антирекорд Москвы: светофоры стоят дороже квартир

Mesut Ozil thanks Arsenal fans and shows his favorite moment in the club -Nigerian